The Council has been seeking your views on a proposal to enlarge the school site and increase the number of school places that are available at Drury Primary School.

The Council proposes to deliver the additional school places by:

Increasing the capacity of Drury Primary School from its current provision of 124 full time school places to 180 full time school places, an overall increase of 56 full time places from 1 September 2024.

The proposal would result in the school’s admission number increasing from 17 pupils per year group to 25 pupils per year group. The increase in capacity would be delivered through an extension to the existing school building. It is proposed that the implementation of the new school capacity would be put in place after the building works are completed by 1 September 2024.

The formal consultation period commenced on 1 March 2022 and ended on 11 April 2022.

The consultation report summarising the issues raised during consultation alongside the Council's response was made available at the links below.

A Statutory Notice for the proposal was issued, the statutory notice period ran from 29 September 2022 to 27 October 2022 during which time any person was able to object to the proposal. No objections were received for this proposal.

Decision Notification

On Tuesday 20 December 2022, Flintshire County Council’s Cabinet determined the proposal to increase the capacity of Drury Primary School from its current provision of 124 full time school places to 180 full time school places, an overall increase of 56 full time places from 1 September 2024.

Cabinet considered the proposal and the local authority response in accordance with the requirements of the School Organisation Code 2018. Cabinet decided to approve the proposal.

The decision letter and the objection report are available by following the links below.

Drury Primary School Decision Notification Letter

Drury Primary School Objection Report

This Decision letter and Objection Report are published in hard copy, if you require a paper copy of this document, or a copy of the document in a different format for example braille or large print, or help with interpretation in a different language, please contact the School Modernisation Team on 01352 702188 / 01352 704014, or e-mail 21stCenturySchools@flintshire.gov.uk


Consultation Timeline - Subject to Change

 The proposed timetable for decision making is:

Stage of Process

Key Dates

Consultation process

1 March 2022 to 11 April 2022

Cabinet consider the results of the consultation and determines whether to proceed with proposals

July 2022

Council publish statutory notice and enter into objection period

September 2022

Cabinet consider the objection report and determine whether or not to implement the proposals

November 2022

Decision notification letter is issued with outcome from Cabinet determination